• Hospital Nobo Otrobanda
    Curacao, Curacao Island

    Baumann Consulting provided energy modeling, commissioning, and measurement and verification (M&V) services to optimize the building operation of Hospital Nobo Otrobanda on Curacao Island.

Located on the Caribbean island of Curacao, near the northern coast of Venezuela, this is a modern hospital outfitted with state of the art equipment which reaches back to the history, culture, climate, environment, and population of Curacao in all its facets.

This hospital is to be designed with sustainable and innovative solutions, resulting in an improved living environment and increased well-being now and for the future. The result is a healing environment, which can readily be adjusted and expanded to address future needs.

Baumann performed energy modeling and was able to show a reduction of 35% in annual energy costs compared to the baseline according to ASHRAE 90.1-2007 Appendix G.

During the design phase of the commissioning process our team of engineers identified the following issues:

  • Missing system redundancy for CHW supply as required in OPR
  • Close proximity of emergency generator exhaust flues to air cooled chiller intakes grilles
  • Different sizing and location of utilities (bus bars, CHW, O2, NO2 pipes, and DHW) as designed by the teams for central energy plant and hospital

In addition, Baumann will also perform Measurement and Verification to optimize the building operation in the first year of occupancy.

            

 